Software life cycle overview
Version | Activity | Requirements and system acceptance test specification | Date/ Initials |
V1.3 | Task | Requirements specification | ThangVX AnhMTV |
Method | Peer review | ||
Check | Requirements specification approved | HieuDD | |
 | Design and implementation |  | |
Task | Design and development planning | ThangVX HieuDD | |
Method | Peer review | ||
Task | Design | ThangVX | |
Method | Peer review | HieuDD | |
Check | Design approved | HieuDD | |
 | Coding |  | |
Task | Coding | AnhMTV ThangVX LinhTM TienLQ | |
Method | Peer review | AnhMTV ThangVX LinhTM TienLQ | |
Task | Unit test | AnhMTV ThangVX LinhTM TienLQ | |
Method | Peer review | AnhMTV ThangVX LinhTM TienLQ | |
Check | Deploy to test environment | ThangVX | |
 | Inspections and testing |  | |
Task | Test plan | NhungPTT | |
Method | Peer review | ThangVX | |
Check | Test plan approved | ThangVX | |
Task | Test case | NhungPTT | |
Method | Peer review | ThangVX | |
Check | Test report/ Test approved | NhungPTT | |
Task | Test performance | N/A | |
Method | Test report | ThaoNT | |
 | Installation and system acceptance test |  | |
Task | Installation plan | ThangVX | |
Method | Peer review | AnhMTV LinhTM TienLQ NhungPTT HieuDD | |
Check | Installation plan approved | HieuDD | |
Method | Verification and test of installation | NhungPTT Â | |
Task | System acceptance test preparation | ThangVX | |
Method | System acceptance test | NhungPTT | |
Check | System acceptance test approved | NhungPTT HieuDD | |
 | Performance, servicing, maintenance, phase out |  | |
Task | Phase out | ThangVX | |
Method | Peer review | HieuDD |
Software life cycle activities
Version | 5.1. Requirements and system acceptance test specification | Document/ Initials |
V1.3 | New features: V1.3.1:
V1.3.2:
V1.3.3
| |
Requirements specification | V1.3.1: https://bit.ly/3EO5Cqh  V1.3.2: https://bit.ly/3KlFX9w  V1.3.3: https://bit.ly/3rTCvMT  | |
Peer review | ||
Requirements specification approved | ||
Design and implementation | ||
Design and development planning | N/A | |
Peer review | ||
Design approved | ||
Design changes | N/A | |
Peer review | ||
Coding | ||
Coding | Build: xx – Build: xx | |
Peer review | ||
Unit test | ||
Peer review | ||
Deploy to test environment | ||
Inspections and testing | ||
Test plan | ||
Peer review | ||
Test plan approved | ||
Test case | ||
Peer review | ||
Test report/ Test approved | ||
Test report | ||
Test case changes:
| ||
Peer review | ||
Test approved | ||
Installation and system acceptance test | ||
Installation plan | ||
Peer review | ||
Installation plan approved | ||
Installation summary | ||
Installation procedure | ||
Verification and test of installation | ||
System acceptance test preparation | ||
System acceptance test | ||
System acceptance test approved | ||
Performance, servicing, maintenance, phase out | ||
Phase out | N/A | |
Peer review |